Eight steps, one container, one set of documents. This page is the long version — including the parts clients only discover halfway through: how several factories become one shipment, and which rules at your end decide whether the goods can legally be installed.
Most of this runs without you. The decisions that genuinely need you are marked. Everything else, we would rather you did not have to think about.
A room-by-room list, a budget in your currency, and the city the goods are going to. Photos of rooms you like, or a mood board, help more than dimensions at this stage. A rough list is enough: we would rather start and refine than wait for something perfect.
Needs you: one message.
Each item goes to two or three factories that actually make that category — a sofa factory is not a marble-table factory, and pretending otherwise is how people end up with a bad dining table. You get a comparison with the factory named, the FOB price, the lead time, and freight and duty shown as separate lines rather than folded into one flattering total.
Needs you: a decision on which option, not on which factory.
Fabric swatches and leather samples are shipped to you, or shown on a video call with the factory's sample room. Wood stain, stone slab and hardware finish are confirmed the same way. This is the cheapest hour of the entire project and the one people skip.
Needs you: approve the finish. In writing, ideally.
You sign a single cooperation agreement with our team, and it covers the whole project. A whole-house order can run through ten, twenty, sometimes thirty factories — a separate contract, a separate set of payment terms and a separate round of correspondence for each one is where these projects stall. We are the party you contract with, and we set one payment schedule across every supplier in the project.
The money still goes straight into each factory's own account. We never hold your goods payment and take no margin on it; what we do is keep every invoice pointing at one schedule — deposits in one round, balances before loading, each receipt matched to the right factory and the right item. And the factory quotation reaches you unchanged: stand in a showroom in Foshan and the factory's own sales staff quote you directly. Our income is the 5% service fee and nothing else.
Needs you: sign the cooperation agreement, and pay the deposit.
We visit during production, not only at the end. A frame that is 2cm out is a five-minute fix on the line and an unsellable sofa once it is upholstered and crated. Progress photos and short videos come to you at agreed milestones, so you are not guessing for two months.
Needs you: nothing, unless something has to change.
Every item is checked against the order before it is packed — dimensions, finish, colour consistency across a set, hardware, mechanism, stitching, and whether the quantity matches. Anything that fails is fixed, replaced or credited before it gets on a truck, because after that the only remedy is a claim.
Needs you: read the inspection report. It is written for you, not for the file.
Goods from different factories meet at one warehouse near the port, are counted against the list, crated where the piece needs it, and loaded to a plan. This is the step most people cannot picture, so there is a whole section on it below.
Needs you: nothing.
The full document set is issued before the container moves — commercial invoice, packing list, bill of lading, certificate of origin, and any product certificates your market requires. Then sea freight, your customs broker at the destination, and delivery. You receive one set of documents, not one per factory.
Needs you: nominate a broker, or let us recommend the process.
On timing: the honest answer is a breakdown rather than one number. Custom pieces take about two months to produce. Inspection takes about a week, and that is also the week we settle the shipping with you — sailing, freight rate, and the balance payment. Loading and export clearance take roughly another week once the balance is arranged. Then there is the ship, which depends entirely on where you are. The clock starts when your deposit clears and the drawings are signed off, not when you first ask for a quote.
The windows below are port-to-port transit for a full container, not door delivery. Schedules and rotations move with the season, so use them to plan and let the booking confirm the actual date.
Two things that move it more than anything else. Chinese New Year, when factories close for two to four weeks and the ports get busy before and after — an order placed in November and one placed in January are not the same project. And the finish you choose: a plain fabric and a plain veneer can be run quickly, while lacquer, brushed brass and custom upholstery genuinely cannot be rushed, whatever a supplier says in the first meeting.
If a date matters to you — a handover, a season, a lease ending — tell us the date first and we will work backwards from it. It is a much easier conversation than discovering the gap after the deposit is paid.
This is the part clients find hardest to picture, and the part that goes wrong when nobody owns it. So here is the whole mechanism, in the order it happens.
Not to the port, and not to each other. The factories deliver to a consolidation warehouse we nominate near the port of loading. Goods arrive on different days over one or two weeks, and each delivery is checked in and counted against the order.
We see what has arrived, what is missing, and what is late. Nothing gets loaded until the list is complete — or until you decide to ship without the late item rather than hold the container. That decision is yours, and it is better made with numbers in front of you.
Sofas are wrapped and corner-protected. Marble tops and glass are crated. Loose hardware and legs travel inside the piece, labelled by room, so the fitter knows what belongs to what. Timber crating is the standard for anything fragile — and timber packaging is exempt from EUDR, unlike the furniture itself.
Heavy items low and forward, soft goods filling voids above, nothing resting on a finished surface, and the whole load braced so it cannot shift in heavy weather. A container is not a van: it will roll for thirty days. If the load is not tied down, the sea will rearrange it for you.
A 20ft holds roughly 28 cubic metres, a 40ft about 58, a 40HQ about 68. A whole-house order is usually a 40HQ; a single room or a partial load is often cheaper as LCL, where you pay for the space you use and share the container with other cargo.
Consolidation does not just save freight. It turns nine invoices into one shipment with one packing list and one bill of lading, which is what makes customs at your end a morning's work instead of a week of correspondence.
The consolidation warehouse, the crating and the loading plan are billed at cost and shown as separate lines on your quotation. They are not folded into a single number, because you should be able to see what packing actually costs.
These are not quality problems. The furniture can be flawless and still unusable — because a plug does not fit, a label is missing, or a certificate was never issued. Every one of these is settled before production, not after arrival.
A chandelier that works in Foshan may not be legal in your house. Voltage and frequency differ (230V 50Hz in the UK and EU, 120V 60Hz in North America), plugs differ, and most markets require the fitting to carry recognised certification before a licensed electrician will connect it.
We specify the voltage, plug and certification your market requires at the order stage, because that is when the factory can build it in. Retrofitting a certificate to a finished lamp is not a thing that can be done.
The UK requires domestic upholstered furniture to meet fire safety regulations and to carry a permanent, stapled label saying so. Many Foshan workshops can do this; plenty cannot, particularly on one-off pieces made from a photograph.
Ask before you order, not after. If a factory cannot produce a compliant label, we will say so and offer a different factory or a different fabric rather than let you find out at the doorstep.
Panels and composite wood are the usual source of formaldehyde complaints. E1 is the baseline in most of Europe; CARB P2 and TSCA Title VI apply in the United States; Greenguard Gold is a voluntary certification some factories genuinely hold and others merely mention.
We ask for the mill certificate, not the marketing claim, and it travels with the shipment.
The EU Deforestation Regulation applies to timber furniture placed on the EU market. In practice it means the supplier must be able to give the geolocation of the plot the timber came from, the species, and the due-diligence information behind it. Timber packaging — crates, pallets, frames — is exempt; the furniture is not.
FSC certification is not the same thing as EUDR compliance. If you are importing into the EU, ask your supplier for the plot data now, because it cannot be reconstructed later.
None of this is a reason to avoid buying from China. It is a reason to settle it in writing before the deposit, which is where we start every order.
Dimensions against the approved drawing. Colour consistency across a set — two sofas from the same batch can still differ. Stitching, seams, piping and button alignment. Hardware, drawer runners, hinges and recliner mechanisms operated, not just looked at. Stone and glass checked for chips under light. Quantity counted against the list. Packing checked before the crate is closed.
You get photographs and a written report, in English, with the failures listed as clearly as the passes.
Photograph the packaging before you open it, and the piece before it is moved. Damage that happened in transit is an insurance claim; damage that left the factory is a supplier claim, and the two are decided by those photographs. Send them within the claim window rather than after the room is finished.
We raise it with the factory or the insurer on your behalf, and stay on it. Structural failure inside the first year is covered by the factory warranty; maintenance and spare parts after that we handle for the life of the piece.
Send it as it is. We will come back with the questions that actually matter — destination, timing, and which pieces need a standard your market will check.